Ashford and St Peters Hospitals NHS Foundation Trust: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service

  Ashford and St Peters Hospitals NHS Foundation Trust has published this notice through Delta eSourcing

Notice Summary
Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
Notice type: Competitive Contract Notice
Authority: Ashford and St Peters Hospitals NHS Foundation Trust
Nature of contract: Not applicable
Procedure: Not applicable
Short Description: The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park. Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network. Scope of the project •Provision and maintenance of utilities to Block 54 until 2020/21; •Diversion of all services currently routed through the Ramp; •Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW; •Grading of the released land and formation of a new 90-spaces tarmacked visitor car park; •Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park; •Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block; •Additional external lighting. Please refer to the attached project brief for more details.
Published: 16/06/2017 11:47

View Full Notice

Competitive Contract Notice

1. Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
2. Awarding Authority:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose
3. Contract Type: Services

4. Description: Building construction work. The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park.
Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network.

Scope of the project

•Provision and maintenance of utilities to Block 54 until 2020/21;
•Diversion of all services currently routed through the Ramp;
•Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW;
•Grading of the released land and formation of a new 90-spaces tarmacked visitor car park;
•Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park;
•Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block;
•Additional external lighting.
Please refer to the attached project brief for more details.
5. CPV Codes:
   45210000 - Building construction work.

6. NUTS Codes :
   UKJ23 - Surrey

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Surrey,
8. Reference Attributed by the Awarding Authority: ASP/TE/17/07
9. Estimated Value of Requirement: Category J: 25K to 50K
Currency: GBP
10. Deadline for Expression of Interest: 30/06/2017 12:00:00
11. Address to which they must be sent:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=263728273
TKR-2017616-PRO-10433732

View any Notice Addenda

GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNotice - GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
1. Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
2. Awarding Authority:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose

4. Description: Building construction work. The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park.
Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network.

Scope of the project

•Provision and maintenance of utilities to Block 54 until 2020/21;
•Diversion of all services currently routed through the Ramp;
•Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW;
•Grading of the released land and formation of a new 90-spaces tarmacked visitor car park;
•Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park;
•Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block;
•Additional external lighting.
Please refer to the attached project brief for more details.


Please email the Expression of interest to the email address provided below

mark.lukose@asph.nhs.uk
5. CPV Codes:
   45210000 - Building construction work.

6. NUTS Codes :
   UKJ23 - Surrey

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Surrey,
8. Reference Attributed by the Awarding Authority: ASP/TE/17/07
9. Estimated Value of Requirement: Category J: 25K to 50K
Currency: GBP
10. Deadline for Expression of Interest: 30/06/2017 12:00:00
11. Address to which they must be sent:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose
   
12. Other Information:
Other Information: To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=263752203

13. Description of Amendment / Addition: Expression of interest submission method - Email Address added TKR-2017616-PRO-10433988


GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNoticeAddendum - GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
1. Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
2. Awarding Authority:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose

4. Description: Building construction work. The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park.
Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network.

Scope of the project

•Provision and maintenance of utilities to Block 54 until 2020/21;
•Diversion of all services currently routed through the Ramp;
•Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW;
•Grading of the released land and formation of a new 90-spaces tarmacked visitor car park;
•Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park;
•Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block;
•Additional external lighting.
Please refer to the attached project brief for more details.


Please email the Expression of interest to the email address provided below

mark.lukose@asph.nhs.uk
5. CPV Codes:
   45210000 - Building construction work.

6. NUTS Codes :
   UKJ23 - Surrey

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Surrey,
8. Reference Attributed by the Awarding Authority: ASP/TE/17/07
9. Estimated Value of Requirement: Category J: 25K to 50K
Currency: GBP
10. Deadline for Expression of Interest: 30/06/2017 12:00:00
11. Address to which they must be sent:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose
   
12. Other Information:
Other Information: To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=263776418

13. Description of Amendment / Addition: Contract Type changed to work TKR-2017616-PRO-10434242


GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNotice - GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
1. Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
2. Awarding Authority:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose, Attn: Mark Lukose
      Sub Type: Design and Execution

4. Description: Building construction work. The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park.
Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network.

Scope of the project

•Provision and maintenance of utilities to Block 54 until 2020/21;
•Diversion of all services currently routed through the Ramp;
•Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW;
•Grading of the released land and formation of a new 90-spaces tarmacked visitor car park;
•Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park;
•Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block;
•Additional external lightings.
5. CPV Codes:
   45210000 - Building construction work.

6. NUTS Codes :
   UKJ23 - Surrey

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Surrey,
8. Reference Attributed by the Awarding Authority: ASP/TE/17/07
9. Estimated Value of Requirement: Category J: 25K to 50K
Currency: GBP
10. Deadline for Expression of Interest: 30/06/2017 12:00:00
11. Address to which they must be sent:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose, Attn: Mark Lukose
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=263758459

13. Description of Amendment / Addition: Added - Inclusion in Contracts Finder TKR-2017616-PRO-10434077

Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 21/08/2017
Period of Work End date: 12/01/2019



Complementary Information
Funding:

GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNoticeAddendum - GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
1. Title: GB-Chertsey: Ramp Demolition and Creation of Car Parks -Fee proposal for Design Team / Lead Design Service
2. Awarding Authority:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose, Attn: Mark Lukose
      Sub Type: Design and Execution

4. Description: Building construction work. The Ramp buildings date back to the1940s and are temporary buildings. These buildings are well beyond their anticipated life span, and have been identified in the Trust 6 Facet Survey as Poor / requiring high cost investment and are energy inefficient. Due to the complexities of demolishing the entire Ramp, the Ramp has been designated in two sections: Upper and Lower Ramp. The Lower Ramp was demolished in 2011/12, and the space was used to create a staff car park.
Ashford and St Peter’s NHS Foundation Trust (The Trust) now wishes to demolish the Upper Ramp and create space for the Trust future developments. The proposed works involves the careful demolition of Block 46, 50, 51, local Boiler Plant room and associated ramp corridor. It also includes services diversion for Bock 54, Asbestos removal, construction of car parks, provision of works compound and an access route for the new Urgent Care and Assessment Block, together with improvement of the road network.

Scope of the project

•Provision and maintenance of utilities to Block 54 until 2020/21;
•Diversion of all services currently routed through the Ramp;
•Demolition of Block 46, 50, 51, local Boiler Plant Room and associated ramp corridor as far as the fire doors in the corridor linking Level 2 DOK and PEW;
•Grading of the released land and formation of a new 90-spaces tarmacked visitor car park;
•Levelling the sloped green area in the main staff car park and designing a new layout for the staff cark park;
•Closure of Hazel Car Park at the end of this project; this car park will be used as a contractor works compound for building the new UCAA Block;
•Additional external lightings.
5. CPV Codes:
   45210000 - Building construction work.

6. NUTS Codes :
   UKJ23 - Surrey

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: Surrey,
8. Reference Attributed by the Awarding Authority: ASP/TE/17/07
9. Estimated Value of Requirement: Category J: 25K to 50K
Currency: GBP
10. Deadline for Expression of Interest: 30/06/2017 12:00:00
11. Address to which they must be sent:
    ASPH NHS Foundation Trust
    St Peter's Hopsital, Guildford Road, Chertsey, Surrey, KT16 0PZ, United Kingdom
    Tel. 01784884766, Email: mark.lukose@asph.nhs.uk, URL: http://www.ashfordstpeters.nhs.uk/
    Contact: Mark Lukose, Attn: Mark Lukose
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=264016508

13. Description of Amendment / Addition: Changed to Open Procedure : TKR-2017619-PRO-10453288

Suitable for VCO: No
Procedure Type:RESTRICTED
Period of Work Start date: 21/08/2017
Period of Work End date: 12/01/2019



Complementary Information
Funding:

View Award Notice